Contents:
- How to Setup Full Backup Rotation for 1 week with Full Backup
- How to Setup Full Backup Rotation for 2 Full Backups rotating every 2 Weeks on Friday and 4 Differential on Monday, Tuesday, Wednesday, Thursday with Overwrite
- Full Backup on Friday and 4 Differential on Monday, Tuesday, Wednesday, Thursday with Overwrite
- Full Backup on Friday and 1 Differential on Monday, Tuesday, Wednesday, Thursday with Overwrite
- Backup Rotation 1 week to a Tape
- How to Setup Full Backup Rotation for 2 weeks with NovaBACKUP
- How to Setup Full Backup Rotation every 4 Fridays
- How to Setup Full Backup Rotation for 2 Backup every 2 Weeks on Friday
How to Setup Full Backup Rotation for 1 week with Full Backup
If you create 5 jobs and schedule them one for each day, then after one week it will start overwriting your old backups and you will have 4 days to go back in case you need to.
- Click on a TAB called Backup, in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select New Backup JOB
- Under Backup Name call it: Monday, then on a bottom left site choose destination and under media name call it: Monday.
- Make Your Backup Selection, and click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA,Set Backup Mode to Full then click OK
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE BACKUP JOB AS and name it Monday, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Monday and choose time, Repeat every.. set to 1 day and select only Monday.
Now From a Main Screen
- Under Backup Name call it: Tuesday, then on a bottom left site choose destination and under media name call it: Tuesday.
- Your Backup Selection Should Be Set.
- From a main Backup Screen in a TOP Left Corner Click on a big N and select SAVE Monday JOB AS and name it Tuesday, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Tuesday and choose time, Repeat every.. set to 1 day and select only Tuesday.
Repeat those steps for Wednesday, Thursday, and Friday
How to Setup Full Backup Rotation for 2 Full Backups rotating every 2 Weeks on Friday and
4 Differential on Monday, Tuesday, Wednesday, Thursday with Overwrite
Total # of Jobs 6
If you create 2 jobs and schedule them one for each day, then after 2 weeks it will start overwriting your old backups
- Click on a TAB called Backup, in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select New Backup JOB
- Under Backup Name call it: Friday1, then on a bottom left site choose destination and under media name call it: Friday1.
- Make Your Backup Selection, and click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA, and Set Backup Mode to Full then click OK
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE BACKUP JOB AS and name it Friday1, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Friday and choose time, Repeat every.. set to 2 day and select only Friday.
Now From a Main Screen
- Under Backup Name call it: Friday2, then on a bottom left site choose destination and under media name call it: Friday2.
- Your Backup Selection Should Be Set.
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE Monday JOB AS and name it Friday2, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose Second Upcoming Friday and choose time, Repeat every.. set to 2 day and select only Friday.
Now We Will Setup Differential
From a Main Screen
- Under Backup Name call it: Monday, then on a bottom left site choose destination and under media name call it: Monday
- Your Backup Selection Should Be Set, click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA, and Set Backup Mode to Differential then click OK
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE Friday JOB AS and name it Monday, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Monday and choose time, Repeat every.. set to 1 day and select only Monday.
Repeat those steps for Tuesday, Wednesday, and Thursday
Full Backup on Friday and 4 Differential on Monday, Tuesday, Wednesday, Thursday with Overwrite
You will have to create 5 jobs
Those steps will create 1 week rotation for you:
- Click on a TAB called Backup, in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select New Backup JOB
- Under Backup Name call it: Friday, then on a bottom left site choose destination and under media name call it: Friday.
- Make Your Backup Selection, and click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA, and Set Backup Mode to Full then click OK
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE BACKUP JOB AS and name it Friday, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Friday and choose time, Repeat every.. set to 1 day and select only Friday.
Now We Will Setup Differential
From a Main Screen
- Under Backup Name call it: Monday, then on a bottom left site choose destination and under media name call it: Monday
- Your Backup Selection Should Be Set, click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA, and Set Backup Mode to Differential then click OK
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE Friday JOB AS and name it Monday, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Monday and choose time, Repeat every.. set to 1 day and select only Monday.
Repeat those steps for Tuesday, Wednesday, and Thursday
Full Backup on Friday and 1 Differential on Monday, Tuesday, Wednesday, Thursday with Overwrite
You will have to create 2 jobs
- Click on a TAB called Backup, in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select New Backup JOB
- Under Backup Name call it: Friday, then on a bottom left site choose destination and under media name call it: Full Backup.
- Make Your Backup Selection, and click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA, Set Backup Mode to Full then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Friday and choose time, Repeat every.. set to 1 day and select only Friday.
Now We Will Setup Differential
From a Main Screen
- Under Backup Name call it: Differential , then on a bottom left site choose destination and under media name call it: Differential
- Your Backup Selection Should Be Set, click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA, Set Backup Mode to Differential then click OK
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE Friday JOB AS and name it Differential, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Monday and choose time, Repeat every.. set to 1 day and select Monday, Tuesday, Wednesday, Thursday.
Backup Rotation 1 week to a Tape
If you create 5 jobs and schedule them one for each day, then after one week it will start overwriting your old backups and you will have 4 days to go back in case you need to.
Those steps will create 1 week rotation for you:
- Click on a TAB called Backup, in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select New Backup JOB
- Under Backup Name call it: Monday, then on a bottom left site choose destination and under media name call it: Monday.
- Make Your Backup Selection, and click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA, Set Backup Mode to Full then click OK
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE BACKUP JOB AS and name it Monday, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Monday and choose time, Repeat every.. set to 1 day and select only Monday.
Now From a Main Screen
- Under Backup Name call it: Tuesday, then on a bottom left site choose destination and under media name call it: Tuesday.
- Your Backup Selection Should Be Set.
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE Monday JOB AS and name it Tuesday, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Tuesday and choose time, Repeat every.. set to 1 day and select only Tuesday.
Do that till you have your Week Set.
How to Setup Full Backup Rotation for 2 weeks with NovaBACKUP
If you create 10 jobs and schedule them one for each day, then after two weeks it will start overwriting your old backups and you will have 8 days to go back in case you need to.
Those steps will create 2 weeks rotation for you:
Click on a TAB called Backup, in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select New Backup JOB
- Under Backup Name call it: Monday1, then on a bottom left site choose destination and under media name call it: Monday1.
- Make Your Backup Selection, and click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA, and Set Backup Mode to Full then click OK
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE BACKUP JOB AS and name it Monday1, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Monday and choose time, Repeat every.. set to 2 day and select only Monday.
Now From a Main Screen
- Under Backup Name call it: Tuesday1, then on a bottom left site choose destination and under media name call it: Tuesday1.
- Your Backup Selection Should Be Set.
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE Monday JOB AS and name it Tuesday1, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Tuesday and choose time, Repeat every.. set to 2 day and select only Tuesday.
Repeat those steps for Wednesday, Thursday, and Friday.
Once you have one week done then Create Second Week:
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE BACKUP JOB AS and name it Monday2, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose Second Upcoming Monday and choose time, Repeat every.. set to 2 day and select only Monday.
Now From a Main Screen
- Under Backup Name call it: Tuesday2, then on a bottom left site choose destination and under media name call it: Tuesday2.
- Your Backup Selection Should Be Set.
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE Monday JOB AS and name it Tuesday2, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose Second Upcoming Tuesday and choose time, Repeat every.. set to 2 day and select only Tuesday…..
How to Setup Full Backup Rotation every 4 Fridays
If you create 4 jobs and schedule them one for each day, then after 4 weeks it will start overwriting your old backups
Click on a TAB called Backup, in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select New Backup JOB
- Under Backup Name call it: Friday1, then on a bottom left site choose destination and under media name call it: Friday1.
- Make Your Backup Selection, and click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA, and Set Backup Mode to Full then click OK
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE BACKUP JOB AS and name it Friday1, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Friday and choose time, Repeat every.. set to 4 day and select only Friday.
Now From a Main Screen
- Under Backup Name call it: Friday2, then on a bottom left site choose destination and under media name call it: Friday2.
- Your Backup Selection Should Be Set.
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE Monday JOB AS and name it Friday2, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose Second Upcoming Friday and choose time, Repeat every.. set to 4 day and select only Friday.
Repeat this for Friday3 and Friday4
How to Setup Full Backup Rotation for 2 Backup every 2 Weeks on Friday
If you create 2 jobs and schedule them one for each day, then after 2 weeks it will start overwriting your old backups
Click on a TAB called Backup, in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select New Backup JOB
- Under Backup Name call it: Friday1, then on a bottom left site choose destination and under media name call it: Friday1.
- Make Your Backup Selection, and click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA, and Set Backup Mode to Full then click OK
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE BACKUP JOB AS and name it Friday1, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Friday and choose time, Repeat every.. set to 2 day and select only Friday.
Now From a Main Screen
- Under Backup Name call it: Friday2, then on a bottom left site choose destination and under media name call it: Friday2.
- Your Backup Selection Should Be Set.
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE Monday JOB AS and name it Friday2, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose Second Upcoming Friday and choose time, Repeat every.. set to 2 day and select only Friday.
Now We Will Setup Differential
From a Main Screen
- Under Backup Name call it: Differential , then on a bottom left side choose destination and under media name call it: Differential
- Your Backup Selection Should Be Set, click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA, and Set Backup Mode to Differential then click OK
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE Friday2 JOB AS and name it Differential, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose First Upcoming Monday and choose time, Repeat every.. set to 2 day and select Monday, Tuesday, Wednesday, Thursday.
Second Differential Job From a Main Screen
- Under Backup Name call it: Differential2 , then on a bottom left side choose New destination and under media name call it: Differential2
- Your Backup Selection Should Be Set, click on settings in bottom right. In settings under Write Mode choose OVERWRITE MEDIA, and Set Backup Mode to Differential then click OK
- From a main Backup Screen in a TOP Left Corner Click on Big "N" NovaStor Logo With Blue and Red Color and select SAVE Differential JOB AS and name it Differential2, then click OK
- On a Bottom Right of Main Screen Click on a Schedule.. Set Type of Schedule to Daily, First Run choose Second Upcoming Monday and choose time, Repeat every.. set to 2 day and select Monday, Tuesday, Wednesday, Thursday.